The bridge replacement project on US 287 in Clarendon is nearing the end of Phase One, according to officials with the TxDOT Childress District.
The box and subgrade work is complete as of last week, and the contractor was anticipating the curb and gutter work would be completed by the end of last week with sidewalks being complete this week.
TxDOT says the plan is to begin pouring the concrete pavement by the week of October 20 with an anticipated date of moving to phase two the end of November.