Traffic will be impacted this week as the Texas Department of Transportation begins the project to replace the US 287 bridge over Clarendon’s drainage canal between Kearney and Gorst Streets.
Lane closures are expected to began Wednesday with concrete barriers being placed on Thursday. See the traffic pattern map here.
Demolition on the sidewalk and roadway along the northside of the Donley County State Bank will begin June 23, weather permitting.
The bridge demolition is now scheduled to start on June 30.
Workers were still evaluating and the sewer line this week, which runs under the drainage canal, to determine how to work around that obstacle during the construction.